RN-003PreliminaryJune 2026

US vs EU Interconnection Queue: Scale, Composition, AI Collision Risk

The US interconnection queue is roughly five times larger than the EU by project count. (Source: LBNL Queued Up 2025; ENTSO-E Statistical Factsheet 2024.) But scale is the wrong variable to focus on. What matters is concentration – by ISO, by technology cluster, and by withdrawal velocity. This note maps where AI load growth is colliding with interconnection capacity, and why the EU permitting gap makes that collision harder to track.

6,449

US generators

across 7 ISOs

7

ISOs tracked

MISO · SPP · CAISO · PJM · NYISO · ISONE · ERCOT

504 GW

EU installed capacity

32 ENTSOE countries

01

Queue scale is not the signal, concentration is

The US queue is roughly five times larger than the EU by project count, but that scale is distributed unevenly. (Source: LBNL Queued Up 2025.) A majority of AI-adjacent interconnection pressure is concentrated in just two ISOs: MISO and SPP. Concentration of this kind amplifies collision risk beyond what aggregate numbers suggest. A single ISO under saturation pressure can block more MW of AI infrastructure than a distributed EU-scale permitting backlog, because the bottleneck is localized and cannot easily be rerouted.

02

AI collision risk is a regional, not national, problem

Texas (ERCOT) and the Midwest (MISO/SPP) are early saturation zones. MISO alone accounted for approximately 20% of total US AI-adjacent interconnection requests in 2024. (Source: LBNL Queued Up 2025; MISO queue filings, AI-adjacent classification.) This geographic concentration means that capital allocation decisions that look balanced at a national level may be highly exposed when mapped to ISO-level queue pressure. Withdrawal velocity is rising in these clusters – a leading indicator that projects are discovering grid constraints after initial capital deployment, not before it.

03

EU structural fragmentation vs US ISO concentration

The EU does not have a single interconnection authority below the ENTSO-E level. This creates a structural asymmetry: EU permitting averages approximately 7.4 years versus roughly 4.2 years in the US, and withdrawal data is not consolidated across member states. (Source: ENTSO-E Statistical Factsheet 2024; LBNL Queued Up 2025.) The UK adds a further complication post-Brexit – limited continental interconnector fallback creates structural scarcity that is not visible in ENTSO-E headline figures. Both markets show withdrawal velocity rising in AI-adjacent technology clusters, but the EU signal is harder to read because the queue data does not exist in a normalized form.

US vs EU, Comparative Assessment

DimensionUSEU
Queue size6,449 generators, highly volumetric, roughly 5× EU by project count. (Source: LBNL Queued Up 2025.)Distributed across 32 country authorities, no consolidated queue. (Source: ENTSO-E Statistical Factsheet 2024.)
AI zonesMISO (20% of AI-adjacent requests), SPP, ERCOT as early saturation marketsNo formal AI-adjacent segmentation. Pressure inferred from hyperscaler site activity.
PermittingRoughly 4.2 years average. ISO-level rules, faster in ERCOT (deregulated). (Source: LBNL Queued Up 2025.)Approximately 7.4 years average. Fragmented national regimes, no single sub-ENTSO-E authority. (Source: ENTSO-E Statistical Factsheet 2024.)
Withdrawal dataWithdrawal velocity rising in AI-adjacent tech clusters; LBNL Queued Up 2025 tracks itWithdrawal data not consolidated; country-level reporting is inconsistent
Signal readinessHigh. ISO queue files, LBNL normalization, regional breakdown available. (Source: LBNL Queued Up 2025; ISO queue public filings.)Low to medium. ENTSO-E factsheet gives capacity totals, not project-level queue data. (Source: ENTSO-E Statistical Factsheet 2024.)